AACE International is a globally recognized professional association for the management and development of cost and schedule professionals. The organization provides a variety of professional certifications, including the AACE-PSP (Planning & Scheduling Professional) certification, designed for professionals who specialize in project scheduling, planning, and control.

Introduction to Planning & Scheduling Professional (PSP) Exam

A PSP is a technical specialist in planning and scheduling with specialized experience in project planning and the production, tracking, updating, forecasting, and analysis of integrated project schedules. Under the AACE International Total Cost Management (TCM) system, the PSP leads the planning and scheduling process. A PSP can interact efficiently, both internal and external, with all project stakeholders.

In each of those chapters, the PSP Certification exam is divided into two main chapters (Planning and Scheduling) and two sections. A glimpse of all these sections could be found in the PSP exam dumps as well:

  • Planning product
  • Schedule maintenance and reporting
  • Schedule development
  • Planning development

Planning is the mechanism by which the length of the project task is added to the schedule is to define the project goals and the orderly tasks required to complete the project (the thought part) and not to be confused with scheduling.

Scheduling is a summary of when it is possible to complete each operation in a project and
It must be finished to be done on schedule. The simplest of schedules displays the beginning and completion of operations of a given period in bar chart format. More complex schedules provide schedule logic, usually in CPM format, and display the critical path and floats associated with each operation. A time series of events and activities that reflect an operational timetable. The schedule describes the relative task start and end times and event occurrence times. On a calendar framework or on an elapsed time scale, a schedule can be presented.

The exam is administered through computer-based testing (CBT) and consists of questions of multiple choice and essay-style questions. This test is a closed book. Programmable or preprogrammed calculators are also allowed (including those with financial functions). See the PSP practice exams to understand the paper format. This exam provides a framework for formally evaluating the expertise and abilities of the person in a subject against generally agreed standards. It recognizes those who have
demonstrated their experience and expertise in planning and scheduling.

 

NO.61 What is the cycle time?

 
 
 
 

NO.62 Using the “normal” schedule, what is the early finish date of activity 10002 and its total float?

 
 
 
 

NO.63 Which statement is true?

 
 
 
 

NO.64 When resource leveling craft labor for a critical path schedule, the scheduler

 
 
 
 

NO.65 Which of the following types of delay will NOT result in a time extension and additional compensation for a contractor?

 
 
 
 

NO.66 Project schedules help control all of the following EXCEPT for_____________________.

 
 
 
 

NO.67 Which of the following are NOT normally included in the project scope statement, either directly or by reference?

 
 
 
 

NO.68 How could the structural steel drawing delay have been prevented?

 
 
 
 

NO.69 Using the “normal” schedule, if you start Activity 7001 on April 1, 2002, and using a 5-day workweek, what the finish date for Activity 7001?

 
 
 
 

NO.70 Each column must be poured in one day. Each column requires 2,000 cubic feet of concrete. The lift bucket has a capacity of 40 cubic feet. How many lifts will be required per column pour?

 
 
 
 

NO.71 Determine the correct formula and date for the late finish for Activity 2002.

 
 
 
 

NO.72 At the end of month one, did the delay to the parking structure foundation delay the project?

 
 
 
 

NO.73 You are developing a detailed critical path schedule for a proposed petrochemical plant. The schedule will become a part of the project baseline document, which will be sent to the company’s board of directors for its consideration. What document or resource is likely to be MOST valuable in determining the schedule’s work activity durations?

 
 
 
 

NO.74 What problems can a soils engineer deal with on a project?

 
 
 
 

NO.75 The sum of all budgets for work scheduled to be accomplished within a given time period is the
____________.

 
 
 
 

NO.76 Which of the following is NOT a tool or technique used to perform scope planning?

 
 
 
 

NO.77 Theoretically construct a summary activity for activities 6001 through 6003. Identify the governing predecessor and successor activities for the hammock:

 
 
 
 

NO.78 All the following describe the critical path of a schedule EXCEPT:

 
 
 
 

NO.79 Using the “crashed” schedule, if you start Activity 2002 on August 12, 2001, what is the finish date for Activity 2002?

 
 
 
 

NO.80 These are the activities on the critical path:

 
 
 
 

NO.81 Assuming a total of 30 lifts per crane per day, what is the maximum number of lifts that could be accomplished using 3 small tower cranes over a 5-day period?

 
 
 
 

NO.82 Which of the following project planning situations is the most frequent contributor to cost overruns?

 
 
 
 

NO.83 Budgeted cost of work scheduled is _______________________.

 
 
 
 

NO.84 What is a key first step in developing a critical path method schedule?

 
 
 
 

NO.85 Based on the stated costs, what percentage of the total cost comes from the 2000 series of activities?

 
 
 
 

Earning the AACE-PSP certification can be a valuable asset for professionals in the planning and scheduling field. It demonstrates a commitment to professional development and a dedication to mastering the skills and knowledge required for success in this field. Additionally, many employers look for this certification as a measure of competency when hiring or promoting professionals in the planning and scheduling field.

 

Valid AACE-PSP Exam Dumps Ensure you a HIGH SCORE: https://www.examcost.com/AACE-PSP-practice-exam.html

         

Related Links: myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt

Leave a comment

Your email address will not be published. Required fields are marked *

Enter the text from the image below